Construction to Begin Next Week on new US-95 Passing Lane North of Cottonwood

Installation of new US-95 passing lane near Ferdinand begins next week

Photo: ITD

COTTONWOOD, ID – The Idaho Transportation Department says construction will commence next week to build a new passing lane on U.S. Highway 95 between Cottonwood and Ferdinand to smooth traffic flow and provide a safer opportunity to pass.

Drivers should expect to slow to 45 mph during working hours and 55 mph during off hours through the work zone. The contractor will be working primarily Monday – Friday during daylight hours. Motorists may encounter intermittent flagging with alternating traffic that could create 15-minute delays.

The 1.1-mile passing lane will be built on the northbound side of US-95 between Windy Loop Road and Lauer Crossing Road. Starting at the existing edge line, workers will construct the new 12-foot-wide concrete passing lane and widen the existing shoulder by 6 feet. All construction is expected to end in August.